Voorhees Township is committed to maintaining and improving our 105 miles of local roads for the safety and convenience of our community. Residents and businesses will be notified when the road program is in their area, and work will occur Monday through Friday from 7:00 AM to 5:00 PM, weather permitting. Some detours may be necessary during concrete and paving work. If you have any questions or concerns, please contact the Voorhees Engineering Department at (856) 428-5914. Schedule subject to change. ย All updates will be included in this post.

************************************************************

Ongoing:

Evesham Road Pedestrian Improvements (Phase III โ€“ Kresson Road to Township line)

Completed:

Burnt Mill Road Pedestrian Improvements (Phase II โ€“ Somerdale Road to Britton Place)

Road striping various roads

Miscellaneous concrete improvements (various roads)

Additional paving (various roads)

Miscellaneous crack sealing (crack sealing various roads)

Centennial Blvd (Kresson Rd to Cooper Medical Center), Partridge Dr., Willowbrook Way, Partridge Dr to Sandpiper Dr, Victor Blvd. (Woodstone to Bronwood Dr) – mill and pave

American Way, Cherry Street, Lucas Lane paving

Lucas Lane (Wayside Ln) – patch

Kirkwood Park โ€“ Bike Path

American Way, Cherry Street, Lucas Lane milling

Linden and S. 2nd Street – paving

Chippenham Drive โ€“ Phase II paving (Woodhurst Drive to Bradford Way)

Chippenham Drive – Milling Phase II (Woodhurst Drive to Bradford Way)

Battery, Hanley, S. Terrace, Flamingo, Heron Bittern, E. Evesham driveways, Brambling Lane – paving

S. Terrace milling and paving

Lennox, Ford, Walnut, Chestnut street paving

South Terrace Boulevard (at intersection with Rt. 73)

Sequoia Court concrete work and paving

Laurel Oak Road (Phase II โ€“ Flyers Skate Zone to Haddonfield-Berlin Road)

Covington paving

Battery Hill and Henley Milling

Lennox Ave concrete work & paving

Linden Ave concrete work

Chestnut Ave concrete work

Walnut Ave concrete work

Second Street concrete work

Old Egg Harbor Road Bike Path

Covington Lane – Milling

All inlet upgrades / drainage work

Brambling Lane concrete work

Covington Lane concrete work

Ford Street concrete work

Heron Court concrete work

Flamingo Court concrete work

Bittern Court concrete work

Maiaroto Park concrete workChippenham Drive concrete work

Battery Hill Drive concrete work (Phase II โ€“ WM Feather Drive to Egret Road)

South Terrace Blvd concrete work

Henley Lane concrete work

*************************************************************
๐Ÿฎ๐Ÿฌ๐Ÿฎ๐Ÿฐ ๐—ฅ๐—ข๐—”๐——๐—ฆ:
Laurel Oak Road โ€“ Phase II (Flyers Skate Zone to Haddonfield-Berlin Road (CR 561)
Covington Lane- Phase I (Kresson Road to Elliot Drive)
Lennox Avenue (1/2 Width Paving)
Ford Street (1/2 Width Paving, Other Half Paved by NJ American Water Co)
Linden Avenue (Front Street to Dead End)
Chestnut Avenue (South Second Street to Burnt Mill Road)
Walnut Avenue (Gibbsboro Road to Burnt Mill Road)
Second Street
Sequoia Court
Heron Court
Bittern Court
Flamingo Court
Battery Hill Drive โ€“ Phase II (William Feather Drive to Egret Road)
Henley Lane.